Penalty for Delay in Supplies
While computing the period of delay in supply the following points should be taken into account
- The “delivery period” includes extended delivery period also
- The delivery period is computed from the date of amendment in the supply order only when it is so stipulated their in ,otherwise the delivery period mentioned in the supply order shall be adhered to
- In case of phased delivery ,the period of delay is worked out in respect of each consignment which is supplied after the expiry of the due date
- If the request for inspection is made by a contractor within the delivery period and on inspection the stores are accepted ,no penalty is imposed even if the inspection is carried out after the expiry of the delivery period
- If the first call for inspection of stores is found to be fake or the stores are found to be substandard on inspection and hence rejected but subsequent call is made after the expiry of the delivery period and the stores are found acceptable on inspection the consignment is treated as belated supply period
- Delivery period is to be counted from the date of placement of supply orders in each case and not from the date of expiry of the rate contract
- In computing the period for imposition of penalty the crucial date is the date of expiry of delivery period and the date on which an offer has been made by the contractor for inspection of stores which have been found to be acceptable. As such the date of inspection and issuance of inspection note are immaterial for the purpose of computing the period of delay
- Ordinarily the contractor is required to dispatch the stores within 14 days of the receipt of inspection note indicating acceptance of stores. In case the time taken in dispatching the stores exceeds 14 days, the excess period is counted towards delay for the purpose of levy of penalty unless condoned by the I.O for just and sufficient cause in this behalf by the contractor
- For working out quantum of penalty for a period of part of a month in excess of complete calendar months, the month will be taken as comprising of 30 days and the value of stores shall exclude sales tax but include statutory duties
IIIustration
The delivery period expires on 15-06-1983 and letter dated 14-06-1983 is sent by the contractor to the Indenting officer requesting for inspection of stores. The inspection is carried out on 30-06-1983 and the inspection note is issued on 10-07-1983.On inspection the stores were found to be acceptable and stores were actually received at destination on 25-07-1983. There is no delay in supplies and hence no penalty can be imposed on the contractor because the offer for inspection has been made within the delivery period and the stores have been found acceptable on inspection.
The delivery period expires on 15-06-1983 .The contractor makes the first call on 15-05-1983,and inspection carried out on 30-05-1983 when either the stores are not found on the premises or they are found to be sub-standard and hence rejected .The subsequent offer is made on 19-06-1983 i.e.4 days after the expiry of the delivery period and on inspection which is carried out on 1st July,1983,the stores are accepted. This is a case of delayed supplies because the guanine offer for inspection of store of delay is only 4 days i.e from 15-06-1983 to 19-06-1983 and the penalty is ,therefore, leviable @ 2% for the period on the value of delayed supplies.